Florida Statutes
Part I - General Provisions (Ss. 166.011-166.0497)
166.033 - Development permits and orders.


(1) Within 30 days after receiving an application for approval of a development permit or development order, a municipality must review the application for completeness and issue a letter indicating that all required information is submitted or specifying with particularity any areas that are deficient. If the application is deficient, the applicant has 30 days to address the deficiencies by submitting the required additional information. Within 120 days after the municipality has deemed the application complete, or 180 days for applications that require final action through a quasi-judicial hearing or a public hearing, the municipality must approve, approve with conditions, or deny the application for a development permit or development order. Both parties may agree to a reasonable request for an extension of time, particularly in the event of a force majeure or other extraordinary circumstance. An approval, approval with conditions, or denial of the application for a development permit or development order must include written findings supporting the municipality’s decision. The timeframes contained in this subsection do not apply in an area of critical state concern, as designated in s. 380.0552 or chapter 28-36, Florida Administrative Code.

(2)(a) When reviewing an application for a development permit or development order that is certified by a professional listed in s. 403.0877, a municipality may not request additional information from the applicant more than three times, unless the applicant waives the limitation in writing.
(b) If a municipality makes a request for additional information and the applicant submits the required additional information within 30 days after receiving the request, the municipality must review the application for completeness and issue a letter indicating that all required information has been submitted or specify with particularity any areas that are deficient within 30 days after receiving the additional information.
(c) If a municipality makes a second request for additional information and the applicant submits the required additional information within 30 days after receiving the request, the municipality must review the application for completeness and issue a letter indicating that all required information has been submitted or specify with particularity any areas that are deficient within 10 days after receiving the additional information.
(d) Before a third request for additional information, the applicant must be offered a meeting to attempt to resolve outstanding issues. If a municipality makes a third request for additional information and the applicant submits the required additional information within 30 days after receiving the request, the municipality must deem the application complete within 10 days after receiving the additional information or proceed to process the application for approval or denial unless the applicant waived the municipality’s limitation in writing as described in paragraph (a).
(e) Except as provided in subsection (5), if the applicant believes the request for additional information is not authorized by ordinance, rule, statute, or other legal authority, the municipality, at the applicant’s request, shall proceed to process the application for approval or denial.

(3) When a municipality denies an application for a development permit or development order, the municipality shall give written notice to the applicant. The notice must include a citation to the applicable portions of an ordinance, rule, statute, or other legal authority for the denial of the permit or order.
(4) As used in this section, the terms “development permit” and “development order” have the same meaning as in s. 163.3164, but do not include building permits.
(5) For any development permit application filed with the municipality after July 1, 2012, a municipality may not require as a condition of processing or issuing a development permit or development order that an applicant obtain a permit or approval from any state or federal agency unless the agency has issued a final agency action that denies the federal or state permit before the municipal action on the local development permit.
(6) Issuance of a development permit or development order by a municipality does not create any right on the part of an applicant to obtain a permit from a state or federal agency and does not create any liability on the part of the municipality for issuance of the permit if the applicant fails to obtain requisite approvals or fulfill the obligations imposed by a state or federal agency or undertakes actions that result in a violation of state or federal law. A municipality shall attach such a disclaimer to the issuance of development permits and shall include a permit condition that all other applicable state or federal permits be obtained before commencement of the development.
(7) This section does not prohibit a municipality from providing information to an applicant regarding what other state or federal permits may apply.
History.—s. 2, ch. 2006-88; s. 3, ch. 2012-205; s. 3, ch. 2013-92; s. 3, ch. 2013-193; s. 2, ch. 2013-213; s. 8, ch. 2019-165; s. 3, ch. 2021-224.

Structure Florida Statutes

Florida Statutes

Title XII - Municipalities

Chapter 166 - Municipalities

Part I - General Provisions (Ss. 166.011-166.0497)

166.011 - Short title.

166.021 - Powers.

166.0213 - Governing body meetings.

166.031 - Charter amendments.

166.032 - Electors.

166.033 - Development permits and orders.

166.041 - Procedures for adoption of ordinances and resolutions.

166.0415 - Enforcement by code inspectors; citations.

166.04151 - Affordable housing.

166.042 - Legislative intent.

166.0425 - Sign ordinances.

166.043 - Ordinances and rules imposing price controls; findings required; procedures.

166.0435 - Amateur radio antennas; construction in conformance with federal requirements.

166.044 - Ordinances relating to possession or sale of ammunition.

166.0442 - Criminal history record checks for certain municipal employees and appointees.

166.0443 - Certain local employment registration prohibited.

166.0444 - Employee assistance programs; public records exemption.

166.0445 - Family day care homes; local zoning regulation.

166.0446 - Prohibition of fees for first responder services.

166.04465 - Rules and ordinances relating to towing services.

166.0447 - Municipal park entrance fee discounts.

166.045 - Proposed purchase of real property by municipality; confidentiality of records; procedure.

166.0451 - Disposition of municipal property for affordable housing.

166.047 - Telecommunications services.

166.048 - Conservation of water; Florida-friendly landscaping.

166.0481 - Sanitary sewer lateral inspection programs for municipalities.

166.0483 - Permit may not be required for owner to paint residence.

166.0484 - Ordinances, regulations, and policies concerning temporary underground power panels.

166.0485 - Establishment of neighborhood crime watch programs.

166.049 - Municipal law enforcement agencies; communications and assistance.

166.0493 - Powers, duties, and obligations of municipal law enforcement agencies.

166.0495 - Interlocal agreements to provide law enforcement services.

166.0497 - Alteration, amendment, or expansion of established downtown development district; procedures.