California Code
ARTICLE 5 - Cancellation
Section 51282.3.

51282.3. (a) The landowner may petition the board or council, pursuant to Section 51282, for cancellation of any contract or of any portion of a contract if the board or council has determined that agricultural laborer housing is not a compatible use on the contracted lands. The petition, and any subsequent cancellation based thereon, shall (1) particularly describe the acreage to be subject to cancellation; (2) stipulate that the purpose of the cancellation is to allow the land to be used exclusively for agricultural laborer housing facilities; (3) demonstrate that the contracted lands, or portion thereof, for which cancellation is being sought are reasonably necessary for the development and siting of agricultural laborer housing; and (4) certify that the contracted lands, or portion thereof, for which cancellation is being sought, shall not be converted to any other alternative use within the first 10 years immediately following the cancellation.

The petition shall be deemed to be a petition for cancellation for a specified alternative use of the land. The petition shall be acted upon by the board or council in the manner prescribed in Section 51283.4. However, the provisions of Section 51283 pertaining to the payment of cancellation fees shall not be imposed except as provided in subdivision (b).

(b) If the owner of real property is issued a certificate of cancellation of contract based on subdivision (a), there shall be executed and recorded concurrently with the recordation of the certificate of cancellation of contract, a lien in favor of the county, city or city and county in the amount of the fees which would otherwise have been imposed pursuant to Section 51283. Those amounts shall bear interest at the rate of 10 percent per annum. The lien shall particularly describe the real property subject to the lien, shall be recorded in the county where the real property subject to the lien is located, and shall be indexed by the recorder in the grantor index to the name of the owner of the real property and in the grantee index in the name of the county or city or city and county. From the date of recordation, the lien shall have the force, effect and priority of a judgment lien. The board or council shall execute and record a release of lien if, after a period of 10 years from the date of the recordation of the certificate of cancellation of contract, the real property subject to the lien has not been converted to a use other than agricultural laborer housing. In the event the real property subject to the lien has been converted to a use other than agricultural laborer housing, or the construction of agricultural laborer housing has not commenced within a period of one year from the date of recordation of the certificate of cancellation of contract, then the lien shall only be released upon payment of the fees and interest for which the lien has been imposed. Where construction commences after the one-year period, the amount of the interest shall only be for that period from one year following the date of the recordation of the certificate of cancellation of contract until the actual commencement of construction.

(Amended by Stats. 1999, Ch. 1018, Sec. 8. Effective January 1, 2000.)