22172.4. (a) If the local agency elects to award a project pursuant to this chapter, retention proceeds withheld by the local agency from the design-build entity shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation. Work performed to establish the guaranteed maximum price shall not be subject to retention.
(b) In a contract between the design-build entity and a subcontractor, and in a contract between a subcontractor and any subcontractor thereunder, the percentage of the retention proceeds withheld shall not exceed the percentage specified in the contract between the local agency and the design-build entity. If the design-build entity provides written notice to any subcontractor that is not a member of the design-build entity, before or at the time the bid is requested, that a bond may be required, and the subcontractor subsequently is unable or refuses to furnish a bond to the design-build entity, then the design-build entity may withhold retention proceeds in excess of the percentage specified in the contract between the local agency and the design-build entity from any payment made by the design-build entity to the subcontractor.
(Added by Stats. 2022, Ch. 243, Sec. 1. (SB 991) Effective January 1, 2023. Repealed as of January 1, 2029, pursuant to Section 22174.)