(a) After the deadline established by the commissioners for filing an application has passed, the commissioners shall open and review each application to determine whether it is consistent with the terms of the request for applications and meets the requirements of AS 43.90.130. The commissioners shall reject as incomplete an application that does not meet the requirements of AS 43.90.130.
(b) To evaluate whether an application should be rejected under (a) of this section, the commissioners may request additional information relating to the application.
(c) If, within the time specified by the commissioners, the applicant fails to provide the additional information requested under (b) of this section, or submits additional information that is not responsive, the application shall be rejected.
(d) For an application not rejected under this section, the commissioners shall make a determination that the application, including any requested additional information, is complete.
(e) Except as provided under AS 43.90.150, and after determining which applications are complete, the commissioners shall make all applications available to the legislature.
Structure Alaska Statutes
Title 43. Revenue and Taxation
Chapter 90. Alaska Gasline Inducement Act
Article 2. Alaska Gasline Inducement Act License.
Sec. 43.90.110. Natural gas pipeline project construction inducement.
Sec. 43.90.120. Request for applications for the license.
Sec. 43.90.130. Application requirements.
Sec. 43.90.140. Initial application review; additional information requests; complete applications.
Sec. 43.90.150. Proprietary information and trade secrets.
Sec. 43.90.160. Notice, review, and comment.
Sec. 43.90.170. Application evaluation and ranking.
Sec. 43.90.180. Notice to the legislature of intent to issue license; denial of license.
Sec. 43.90.190. Legislative approval; issuance of license.
Sec. 43.90.200. Certification by regulatory authority and project sanction.
Sec. 43.90.210. Amendment of or modification to the project plan.
Sec. 43.90.220. Records, reports, conditions, and audit requirements.
Sec. 43.90.230. License violations; damages.
Sec. 43.90.240. Abandonment of project.
Sec. 43.90.250. Alaska Gasline Inducement Act coordinator.
Sec. 43.90.260. Expedited review and action by state agencies.