8-1-40-1. "Commission" - Sec. 1. As used in this chapter, "commission" refers to...
8-1-40-2. "Customer" - Sec. 2. As used in this chapter, "customer" means a...
8-1-40-3. "Distributed Generation" - Sec. 3. (a) As used in this chapter, "distributed generation"...
8-1-40-4. "Electricity Supplier" - Sec. 4. (a) As used in this chapter, "electricity supplier"...
8-1-40-5. "Excess Distributed Generation" - Sec. 5. As used in this chapter, "excess distributed generation"...
8-1-40-6. "Marginal Price of Electricity" - Sec. 6. As used in this chapter, "marginal price of...
8-1-40-7. "Net Metering Tariff" - Sec. 7. As used in this chapter, "net metering tariff"...
8-1-40-8. "Premises" - Sec. 8. As used in this chapter, "premises" means a...
8-1-40-9. "Regional Transmission Organization" - Sec. 9. As used in this chapter, "regional transmission organization"...
8-1-40-10. Availability of Electricity Supplier's Net Metering Tariff; Aggregate Net Metering Facility Nameplate Capacity Under Tariff - Sec. 10. Subject to sections 13 and 14 of this...
8-1-40-11. Changes to Net Metering Tariffs Prohibited Before July 1, 2047; Expiration of Net Metering Tariffs After June 30, 2022 - Sec. 11. (a) Except as provided in sections 12 and...
8-1-40-12. Amendment of Commission's Net Metering Rules and Electricity Suppliers' Net Metering Tariffs; Increase to Aggregate Net Metering Facility Nameplate Capacity; Reservation of Capacity for Residential Customers and Organic Waste Biomass Facil... - Sec. 12. (a) Before January 1, 2018, the commission shall...
8-1-40-13. Installations of Net Metering Facilities After December 31, 2017, and Before Expiration of Tariff; Continued Service Under Tariff; Successors in Interest - Sec. 13. (a) This section applies to a customer that...
8-1-40-14. Installations of Net Metering Facilities Before January 1, 2018; Continued Service Under Tariff; Successors in Interest - Sec. 14. (a) This section applies to a customer that...
8-1-40-15. Electricity Supplier's Duty to Procure Customers' Excess Distributed Generation; Amounts Credited to Customers to Be Recognized in Fuel Adjustment Proceedings - Sec. 15. An electricity supplier shall procure the excess distributed...
8-1-40-16. Electricity Supplier's Petition for Rate for Excess Distributed Generation; Annual Submission of Updated Rate - Sec. 16. Not later than March 1, 2021, an electricity...
8-1-40-17. Commission's Review of Rate Petition; Notice and Hearing; Approval of Rate; Calculation - Sec. 17. The commission shall review a petition filed under...
8-1-40-18. Credit on Customer's Monthly Bill for Excess Distributed Generation; Excess Credit Carried Forward - Sec. 18. An electricity supplier shall compensate a customer from...
8-1-40-19. Electricity Supplier's Petition to Commission for Recovery of Energy Delivery Costs Attributable to Distributed Generation Customers; Approval; Findings by Commission - Sec. 19. (a) To ensure that customers that produce distributed...
8-1-40-20. Electricity Supplier to Provide Necessary Metering Equipment; Recovery of Costs - Sec. 20. (a) An electricity supplier shall provide and maintain...
8-1-40-21. Commission's Net Metering and Interconnection Rules; Application to Distributed Generation; Permitted Changes to Rules - Sec. 21. (a) Subject to subsection (b) and sections 10...
8-1-40-22. Distributed Generation Customer's Duty to Comply With Standards - Sec. 22. A customer that produces distributed generation shall comply...
8-1-40-23. Distributed Generation Equipment; Customers' Rights; Attorney General to Adopt Rules - Sec. 23. (a) A customer that produces distributed generation has...