32-27-3-1. Definitions - Sec. 1. The following definitions apply throughout this chapter: (1)...
32-27-3-2. Notice of Claim; Response - Sec. 2. (a) At least sixty (60) days before filing...
32-27-3-3. Action for Construction Defect; Notice of Rejection; Notice to Terminate Offer or Proposal - Sec. 3. (a) If the construction professional disputes the claim...
32-27-3-4. Reasonable Access for Inspection; Action for Construction Defect; Notice of Rejection; Notice to Terminate Offer or Proposal - Sec. 4. (a) If the construction professional makes a proposal...
32-27-3-5. Notice of Acceptance; Reasonable Access to Complete Construction; Agreement to Alter Offer - Sec. 5. (a) To accept the offer of a construction...
32-27-3-6. Dismissal - Sec. 6. Any action commenced by a claimant before compliance...
32-27-3-7. Commence Action for Construction Defect - Sec. 7. Nothing in this section may be construed to...
32-27-3-8. Amend Notice of Claim; Date of Original Notice of Claim Applies - Sec. 8. (a) Before commencing any action alleging a construction...
32-27-3-9. Attorney's Fees and Costs to Construction Professional; Deduction of Sums Paid Under Warranty; Failure to Comply - Sec. 9. (a) If a claimant: (1) unreasonably rejects a...
32-27-3-10. Attorney's Fees and Costs to Claimant - Sec. 10. If a construction professional unreasonably: (1) disputes a...
32-27-3-11. Filing; List of Defects - Sec. 11. (a) In every action brought against a construction...
32-27-3-12. Notice of Right to Offer to Cure; Action Not Barred - Sec. 12. (a) Upon entering into a contract for sale,...
32-27-3-13. Contractual Relationship Not Affected - Sec. 13. Nothing in this chapter shall be construed to...
32-27-3-14. Tolling of Statute of Limitations - Sec. 14. If a written notice of claim is served...