§ 43-1-1401. Legislative Declaration - Source: L. 99: Entire part added, p. 256, § 1,...
§ 43-1-1402. Definitions - As used in this part 14: (4.5) "Force majeure" means...
§ 43-1-1403. Authority to Use a Design-Build Contract Process - Notwithstanding any other provision of law to the contrary, the...
§ 43-1-1404. Criteria - Source: L. 99: Entire part added, p. 258, § 1,...
§ 43-1-1405. Public Notice Procedures - At least forty-five days prior to the anticipated date of...
§ 43-1-1406. General Procedures - Source: L. 99: Entire part added, p. 258, § 1,...
§ 43-1-1407. Stipulated Fee - At its discretion, the department may award a stipulated fee...
§ 43-1-1408. Commission Approval Required - The department shall obtain approval from the transportation commission prior...
§ 43-1-1409. Rule-Making Authority - Source: L. 99: Entire part added, p. 260, § 1,...
§ 43-1-1410. Utility Relocation - Legislative Declaration - Source: L. 2000: Entire section added, p. 1611, § 3,...
§ 43-1-1411. Project Specific Utility Relocation Agreements - Source: L. 2000: Entire section added, p. 1613, § 3,...