§ 15-57-401. Title - This subchapter shall be known and may be cited as...
§ 15-57-402. Definitions - As used in this subchapter: (1) “Active” means a quarry...
§ 15-57-403. Notification — Filing — Public notice and response - (a) It shall be unlawful for any operator to engage...
§ 15-57-404. Notification of intent to quarry - (a) (1) Except for operators of quarries excluded by §...
§ 15-57-405. Notification of temporarily closed quarry - (a) Quarry sites in which operations are only occasionally conducted...
§ 15-57-406. Notification of reactivated quarry - Prior to resuming operation in a temporarily closed quarry, an...
§ 15-57-407. Notification refiling required - (a) Every five (5) years all notifications of intent to...
§ 15-57-408. Notifications of exhausted quarry - (a) When a quarry becomes exhausted, the operator will notify...
§ 15-57-409. Reclamation of land at exhausted quarry site - (a) When the quarry is exhausted, the planned reclamation of...
§ 15-57-410. Site safety - The quarry operator will take the following measures to safeguard...
§ 15-57-411. Complaints of violations of this subchapter - (a) The operator is required to document and respond to...
§ 15-57-412. Bond - (a) In order to assure that all reclamation is completed...
§ 15-57-413. Hearing - An operator may request and obtain an adjudicatory hearing and...
§ 15-57-414. Distribution of fees, fines, and forfeiture amounts - (a) The Division of Environmental Quality shall collect fees, fines,...